What must the Contractor do if the City finds deficiencies in the System during Acceptance Tests?

Study for the San Francisco Housing Portal Contractor Agreement Exam. Engage with flashcards and multiple-choice questions, each question has hints and explanations. Prepare for your certification!

If the City identifies deficiencies in the System during Acceptance Tests, the Contractor is required to correct these problems within one Sprint. This action is crucial as it ensures that the Contractor addresses any issues promptly, adhering to the agreed-upon timelines and standards of the project. Responding effectively to deficiencies demonstrates the Contractor's commitment to quality and helps maintain the integrity of the overall project.

Addressing deficiencies within a specific timeframe, such as a Sprint, is part of agile project management methodologies. It emphasizes iterative progress and continuous improvement, allowing for rapid adjustments and refinements based on feedback. By resolving the issues quickly, the Contractor not only aligns with the project goals but also fosters a collaborative relationship with the City, enhancing trust and accountability in the process.

Other choices, such as ignoring the findings or submitting a report without taking action, would not adequately address the City's concerns and could lead to further delays or complications in project acceptance. Additionally, requesting additional testing without first correcting the deficiencies does not fulfill the Contractor's obligation to resolve issues identified during the Acceptance Tests. Therefore, the requirement to correct the problems within one Sprint is essential for ensuring the project's success and maintaining compliance with contractual obligations.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy