What happens if the Contractor does not promptly commence correction of defects?

Study for the San Francisco Housing Portal Contractor Agreement Exam. Engage with flashcards and multiple-choice questions, each question has hints and explanations. Prepare for your certification!

When the Contractor does not promptly commence the correction of defects, the City has the right to stop work on the Project. This provision serves as a protective measure for the City to ensure that the Project meets the required standards and is completed in a timely manner. By stopping work, the City can also assess the situation and determine the best course of action to address the ongoing issues with the Contractor. This approach helps maintain the integrity of the Project and ensures that any defects are resolved effectively, rather than allowing them to cause further delays or complications.

In contrast, options that suggest overlooking the delay or granting additional time do not uphold the standards expected in a contractor agreement, potentially allowing ongoing issues to persist. Ceasing all operations related to the Project, while a severe measure, is not typically implied as the immediate response without first addressing the specific situations regarding defects. Therefore, the right to stop work on the Project is a clear and direct response to the Contractor's failure to act promptly.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy