What action should be taken by the Contractor in response to a City Project Manager's directive that may affect project performance?

Study for the San Francisco Housing Portal Contractor Agreement Exam. Engage with flashcards and multiple-choice questions, each question has hints and explanations. Prepare for your certification!

The appropriate action for the Contractor in response to a City Project Manager's directive that could impact project performance is to immediately report any concerns to the City's Project Manager. This approach underscores the importance of communication and clarity within the project management framework.

By bringing concerns directly to the attention of the Project Manager, the Contractor ensures that any potential issues are addressed collaboratively and that there is an opportunity to clarify the directive. This not only helps to maintain project integrity but also aids in documenting concerns, which can be vital for accountability and future reference. Open lines of communication can foster a more effective working relationship, allowing for adjustments to be made if needed and keeping the project aligned with its objectives.

In situations where a directive may create uncertainty or conflict, prompt reporting allows for timely intervention, rather than risking project delays or complications that may arise from a lack of dialogue.