If the City stops the work appropriately, what is the Contractor entitled to?

Study for the San Francisco Housing Portal Contractor Agreement Exam. Engage with flashcards and multiple-choice questions, each question has hints and explanations. Prepare for your certification!

When the City stops the work in a manner that is appropriate, the Contractor is entitled to reimbursement for specific costs they have incurred as a result of the work stoppage, along with a time extension for the project. This entitlement recognizes that the Contractor has likely incurred expenses for materials, labor, or other costs up to the point of the stop-work order and that their project timeline has been affected by this decision.

Reimbursement for specific costs ensures that the Contractor is made whole for the financial burden imposed by the work stoppage. Additionally, the time extension acknowledges that the work stoppage may hinder the Contractor's ability to meet originally agreed-upon deadlines, providing a fair way to accommodate changes to the project schedule resulting from the stoppage. This provision is typically included in contractual agreements to protect the interests of the Contractor while also maintaining the city's right to halt work when necessary.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy