How long does the contractor have to provide a cost estimate upon receipt of a City Proposed Change Order?

Study for the San Francisco Housing Portal Contractor Agreement Exam. Engage with flashcards and multiple-choice questions, each question has hints and explanations. Prepare for your certification!

The correct timeframe for a contractor to provide a cost estimate upon receipt of a City Proposed Change Order is ten working days. This requirement is significant because it ensures timely response and communication between the contractor and the city. It allows the city to assess the changes and budget adjustments in a reasonable time frame, facilitating efficient project management and adherence to deadlines.

In construction and contracting, timely estimates are vital for keeping the project on schedule and ensuring all parties involved are on the same page regarding any proposed changes, which can affect overall project costs and timelines. The specificity of ten working days helps eliminate ambiguity and sets clear expectations for both the contractor and the city.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy